Here is an update on where LADWP stands with the construction of the City Trunk Line South Unit 4 (CTLS-4) Project Phase 1 located on Whitsett Avenue at Magnolia Boulevard.
As weather permits, the current work zone on Whitsett Avenue at Magnolia Boulevard is scheduled to be restored on Thursday, December 10, 2015, and a new work zone will be implemented on Whitsett Avenue from Otsego Street to Huston Street. Addison Street will be closed to through traffic on east side of Whitsett Avenue. Construction work in the new work zone is scheduled to be completed in May 2016. Construction will occur Monday through Friday from 7:00 a.m. to 4:00 p.m. with the possibility of occasional work on Saturdays. The entire CTLS-4 Project Phase1 is anticipated to be completed on September 2016.
Traffic on this new work zone will be restricted to only one lane southbound on Whitsett Avenue from Otsego Street to Huston Street, with northbound lanes closed to through traffic. Northbound traffic lanes will be detoured at Riverside Drive for northbound commuters. Local access will be provided. This is the second of three work zones on Whitsett Avenue between Magnolia Boulevard and Riverside Drive that will have northbound closure to commuters.
LADWP will meet with local businesses Wednesday afternoon to discuss the new work zone and project schedule. LADWP will also distribute resident notification letters to local residents.
Download: Resident letter including detour map for northbound commuters (PDF)
Download: Fact sheet with additional information on the Phase 1 and Phase 2 Projects (PDF)
Visit the project website at www.ladwp.com/CTLS4.